The urban population explosion in India in recent years has plunged cities into severe water paucity. Treatment of water and sewage in these cities poses a massive challenge. With our extensive expertise and experience in the field, we offer highly advanced municipal utility solutions, which include:
Project: 144 MLD water treatment plant at sikandra (Agra) on MBBR & UF technology, 10 years of O&M
Commercial framework: DBO under JICA Funding
Project period: 2 yrs. (design & construction) + 3 months trial run + 10 years of O&M
Current status: Completed in all respects, under O&M since 01.07.2014.
Project: 100 MLD sewage treatment plant at Gurgaon (Haryana) on advance ASP technology, 6 years of O&M
Commercial framework: DBO Under HUDA Funding
Project period: 18 months (design & construction) + 3 months trial run + 6 years of O&M
Current status: Under O&M since 31-05-2015.
Project: Sewage & water supply project Including distribution & collection network. maintenance of proposed & existing network for 10 years of O&M
Commercial framework: DBO under state funding
Project period: 30 months (design & construction) + 10 years of O&M
Current status: Under execution as well as O&M of existing as well as new facilities
5 MGD WTP
4.50 MLD STP
83 km water pipeline
113 km sewerage network
Project: 210 MLD Water treatment plant with 5 years O&M
Commercial framework: DBO under KFW Funding
Project period: 15 months (design & construction) + 3 months trial run + 5 years of O&M
Current status: Completed and awaiting inlet water for commissioning
Project :40 MLD sewage treatment plant at Doddabele (Bangalore) on SBR Technology, 10 years of O&M
Commercial framework: DBO Under BWSSB Funding
Project period: 21 Months (Design & Construction) + 3 Month Trial Run + 10 years O&M
Current status: Completed and under O&M from 01.04.2020 onwards
Project :210 MLD intermediate Sewage pumping station at Koramangala Sports Complex (Bangalore), 7 years of O&M
Commercial framework: DBO Under BWSSB funding
Project period: 21 months (design & construction) + 3 months trial run + 10 years O&M
Current status: - Completed and under O&M from 11.09.2020 onwards
Project: Rehabilitation & upgradation of Kondli: Phase I (45.5 MLD), Phase II (113.7 MLD) & Phase III (45.5MLD) Wastewater Treatment Plants (WWTPs).
Consultant: NJS Consultants Ltd + AECOM + TTI & NJS Engineers India
Commercial framework: JICA through NMCG
Project period: 36 months (design & construction) + 6 Month trial run + 1 yr. DLP + 10 years of O&M
Current status: Under execution of Phase-1 & 3 and under O&M of phase-2
Project: Design, financing, construction, rehabilitation, completion, operation and maintenance of the Masani facilities and construction, rehabilitation, operation and maintenance of the Trans-Yamuna facilities on the relevant sites
Consultant: Mahindra
Commercial framework: NMCG
Project period: 21 months + 3 month trial run + 15 years O&M
Current status: Under execution and O&M of existing facilities
STP for HUDA Gurgaon (ASP with power generation) : 100000 M3/Day
WTP for Agra City (MBBR + UF) : 144,000 M3/Day
STP for Kapashera, Delhi, Delhi Jal Board (SBR) : 23,000 M3/Day
STP for Loni, Ghaziabad, U.P. Jal Nigam (MBBR) : 30,000 M3/Day
STP* for Hussain Sagar Lake Project, Hyderabad (UF) : 20,000 M3/Day
STP for Hussain Sagar Lake Project, Hyderabad (ASP- A2O) : 30,000 M3/Day
STP for Ph.III STP at Coronation Pillar, Delhi City (ASP) : 45,500 M3/Day
WTP for Agra City (CONVENTIONAL) : 144,000 M3/Day
STP for Ph.II STP at Coronation Pillar, Delhi City (ASP) : 45,500 M3/Day
STP for Ph.I STP at Coronation Pillar, Delhi City (ASP) : 45,500 M3/Day